Weekly Roadwork Report –TxDOT Atlanta District For July 19-25, 2020

Bowie County

  • SH 8 – At Sulphur River, replacing bridges.
  • SH 93 – Between Meadow Lane and Kennedy Lane, installing sidewalks.
  • FM 2149 – From SH 8 to US 67, seal coating highway.
  • FM 3098 – From FM 2149 to US 67, seal coating highway.

Camp County

  • None

Cass County

  • SH 8 – At Sulphur River, replacing bridges.
  • FM 249 – From 0.3 mile east of FM 785 to FM 3129, seal coating highway.
  • FM 2791 – From SH 77 to US 59, seal coating highway.

Harrison County

  • US 59 – From FM 1997 to Marion County Line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.
  • SH 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.
  • Loop 390 – From US 59 to SH 43 North, repairing and resurfacing highway. Road closed to through-traffic, detour route is signed.
  • FM 1186 – From US 59 to Panola County Line, installing safety end treatments on culverts.

Marion County

  • US 59 – From 1.5 miles south of FM 2208 to Harrison County Line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.

Morris County

  • SH 49 – From Titus County Line to FM 144, repairing and resurfacing highway.

Panola County

  • SH 149 – At SH 315, constructing overpass and widening highway.
  • US 79 – From SH 149 to Rusk County Line, repairing and resurfacing highway.

Titus County

  • SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.
  • US 271—At FM 127 overpass, repairing concrete pavement at bridge approaches.

Upshur County

  • US 271—From Camp County Line to 0.5 mile north of FM 2088, resurfacing highway.

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Marcus Sandifer, Public Information Officer, TxDOT Atlanta District, 903-799-1306, marcus.sandifer@txdot.gov.