  • I-30 – From FM 989 to Arkansas State Line, widening highway. Construction work will begin on shoulders with most of the work being conducted at night.
  • SH 8 – At Sulphur River, replacing bridges.
  • SH 93 – Between Meadow Lane and Kennedy Lane, installing sidewalks.

Camp County

  • None

Cass County

  • SH 8 – At Sulphur River, replacing bridges.

Harrison County

  • US 59 – From FM 1997 to Marion County Line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.
  • SH 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.
  • Loop 390 – From US 59 to SH 43 North, repairing and resurfacing highway. Road closed to through-traffic, detour route is signed.
  • FM 1186 – From US 59 to Panola County Line, installing safety end treatments on culverts.
  • FM 31 – From FM 2625 to FM 451, seal coating highway.

Marion County

  • US 59 – From 1.5 miles south of FM 2208 to Harrison County Line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.

Morris County

  • SH 49 US 79 – From FM 31 to Mill Creek, seal coating highway. – From Titus County Line to FM 144, repairing and resurfacing highway.

Panola County

  • SH 149 – At SH 315, constructing overpass and widening highway.
  • US 79 – From SH 149 to Rusk County Line, repairing and resurfacing highway.
  • US 79 – From FM 31 to Mill Creek, seal coating highway.
  • SH 149 – From FM 124 to FM 959, seal coating highway.
  • FM 699 – From Bus. 79 to FM 2517, seal coating highway.
  • FM 10 – From Bus. 79 to FM 2517, seal coating highway.
  • US 59 – From FM 2517 to FM 999, seal coating highway.

Titus County

  • SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.
  • SH 11 – At Piney Creek, repairing bridge.

Upshur County

  • US 271—From Camp County Line to 0.5 mile north of FM 2088, resurfacing highway.

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Marcus Sandifer, Public Information Officer, TxDOT Atlanta District, 903-799-1306, marcus.sandifer@txdot.gov.