Bowie County
- I-30 – From FM 989 to AR State Line, reconstructing and widening highway, daytime work in median. Motorists should watch for trucks and equipment pulling onto the interstate
- I-30 – Westbound at Exit 207/Spur 594, ramp rehabilitation. Exit ramp closed. I-30 westbound lanes in this area restricted to one lane
- I-30 – Eastbound between US 259 and New Boston, drainage upgrades. Traffic limited to one lane
- SH 8 – At Sulphur River, replacing bridges
- SH 98 – At Anderson Creek, bridge replacement. Traffic restricted to one lane with signal lights controlling traffic through work zone
- FM 2240/Moore’s Lane – From FM 559/Richmond Rd to FM 1397/Summerhill Rd, resurfacing road. Traffic limited to one lane during nightly operations
- SH 93/Summerhill Rd. – From US 67 to I-30, resurfacing road. Lane closures during nightly operations
Camp County
- SL 255 – From FM 1520 to US 271, constructing highway. County Road 2120 detoured
Cass County
- SH 8 – At Sulphur River, replacing bridges
- US 67 – Widening bridge at Jennings Slough. Signal lights controlling one-way traffic
Harrison County
- I-20 – At US 59 overpass, replacing bridge. US 59 traffic shifted to southbound lanes
- I-20 – Concrete pavement repairs. Various daytime lane closures, expect delays
- I-20 – At Lansing Switch Road, constructing new bridge over interstate. Lansing Switch Road closed to through traffic. Possible lane closures on I-20
- SH 43 – At Kansas City Southern Railroad in Karnack, widening bridge over railroad. Signal lights controlling one-way traffic
- US 80 – From Loop 390 to Interstate 20, resurfacing highway. Daytime lane closures, expect delays
- CR 2116 – At Haggerty Creek, replacing bridge. Bridge closed to through traffic
- US 59 – FM 1186 to Panola County line, installing safety barrier cable. Daily lane closures
Marion County
- US 59 – From SH 49 to two miles north of SH 49, repairing and resurfacing highway, possible lane closures
- CR 3306 – At Mill Creek, replacing bridge. Bridge closed to through traffic
Morris County
- SH 49 – From Titus County line to FM 144, repairing and resurfacing highway
Panola County
- US 59 (Loop) – From Business 59 North of Carthage to US 79 East, rehabilitating highway. US 79 traffic shifted to NB lanes at US 59 Loop. US 59 Loop SB exit ramp & NB entrance ramp closed
- CR 224 – At Irons Bayou, replacing bridge. Bridge closed to through traffic
- US 59 – From Harrison County line to Loop 149, installing safety barrier cable. Daily lane closures
Titus County
- SH 49 – From FM 1735 to Morris County line, repairing and resurfacing highway
- SH 49 – From Business 271 to Mount Pleasant city limits, repairing and resurfacing highway. One-lane, two-way traffic
- US 271 – At Dickson Creek, Big Slough Creek, White Oak Creek & White Oak Creek Relief. Replacing bridges
Upshur County
- US 271 – From 5.9 miles north of SH 155 to 1.5 miles north of SH 155, resurfacing highway. Traffic shifted to southbound lanes
Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Heather Deaton, Public Information Officer, TxDOT Atlanta District, 903-799-1306, Heather.Deaton@TxDot.gov